top of page

Policy and Procedure

Info@yeg-snowjob.ca
Sep 28
4 min read

Updated: Oct 18

The City of Edmonton has a Snow and Ice Control Policy, as well as a Snow and Ice Control Procedure, both with reference number C409K over the winter of 2025/26. It is important to understand the difference between these two documents.

The Policy

The Policy was approved by City Council and provides guidelines to support the development of the Procedure. Version C409K was approved by Council on 16 August 2021, and scheduled for review by 16 August 2026. Substantial excerpts from the Policy are provided below:

The purpose of this policy is to set snow and ice control guidelines that support the following outcomes for Edmontonians:

Safety: To prevent or reduce collisions, slips, falls and injury to people, and to ensure that emergency responders can reach those that need help.

Reliability: Edmontonians understand when active pathways and roadways are to be cleared and to what standard they are cleared to.

Connectivity: Edmonton’s snow clearing approach enables Edmontonians to move safely, whether walking, rolling, biking, using transit or driving, through a mobility network of active pathways and roadways.

Guiding Principles

These outcomes will be achieved in accordance with the following guiding principles:

Operational Excellence: Operational decisions will be made to create Edmonton-specific solutions based on continuous improvement, fiscal responsibility, evaluation of new technology and processes as well as ongoing monitoring of current practices.

Environmental Stewardship: Safety and reliability of the winter mobility network will be achieved in a manner that protects the environment and infrastructure assets, and promotes climate resilience.

Equity: Prioritization of winter maintenance activities based on equity is required to provide a mobility network that is accessible to people of all abilities and needs, and for all modes of transportation.

Shared Responsibility: Maintaining a safe and livable winter mobility network is a responsibility shared by the City of Edmonton, Edmonton’s business community and Edmontonians. Collaboration, co-operation, and partnerships are needed to exercise this responsibility effectively.

Public Awareness and Understanding: The City of Edmonton will take a leadership role in increasing public awareness of winter maintenance activities and commit to transparency on how it impacts citizens.


I have highlighted, in blue, several parts of the Policy that will be the subject of future posts.


The Procedure


The Procedure was approved by the City Manager, and provides detailed definitions and procedures to guide the actions of the City Administration, including City Operations. Version C409K was approved by the City Manager on 15 October 2025, and scheduled for review by 26 August 2026.

The Procedure outlines a heirarchical approach to snow and ice management, identified as considering an average snowfall, and based on roadway priorities:

  • Priority 1: Select freeways, arterials, and business districts.

  • Priority 2: Remaining freeways, arterials, and business districts; alleys/back lanes in business districts; collector roadways, transit park and ride access roads.

  • Priority 3: Industrial roadways; rural roadways.

  • Priority 4: Residential roadways and alleys/back lanes.

The Procedure furthermore identifies levels of service for each priority of roadway:

  • Priority 1: Maintain to a bare pavement standard within 24 hours (1 days) following the end of snowfall.

  • Priority 2: Maintain to a bare pavement standard [5 cm snowpack for alleys/back lanes] within 120 hours (5 days) following the end of snowfall.

  • Priority 3: Maintain to a bare pavement standard [level snowpack for rural roadways] within 144 hours (6 days) following the end of snowfall.

  • Priority 4: Maintain to 5 cm snowpack and completed within 240 hours (10 days) once a residential blading cycle is initiated.

 The focus of this web site is on snow and ice management of residential streets (Priority 4), and additional related excerpts from the Procedure are provided below.

  • Procedure Item 2.2.1: Residential roadways (including alleys/back lanes) are cleared only during one of three circumstances: through a residential blading cycle during phase 2 of the parking ban, maintenance blading between snowfall to maintain the snowpack, or in response to 311 notifications.

  • Procedure Item 2.2.2: The decision to initiate a residential blading cycle will be made by the City of Edmonton based on several factors including, but not limited to, residential roadway conditions, current and forecasted weather, a minimum snowpack of 5 cm consistently citywide and status of snow clearing on priority 1, 2 and 3 roadways.

  • Procedure Item 2.2.5: Snow will not be removed from residential roadways unless to permit safe vehicular movement.

  • Procedure Item 2.2.6: Notification of a citywide residential blading cycle will be announced through a variety of communications channels. A phase 2 parking ban will be implemented as explained in section 2.8, Parking Ban.

  • Procedure Item 2.8.1: The City of Edmonton may declare a parking ban at its discretion based on factors including, but not limited to, amount of snowfall, rate of snow accumulation, and current and forecasted conditions.

  • Procedure Item 2.8.2: The parking ban, when declared, will operate in two phases. During Phase 1, no parking is permitted on arterial roadways, within business districts and roadways marked with seasonal no parking signage (collector roadways).

  • Procedure Item 2.8.2 [partial excerpt]:  After Phase 1 is completed, a Phase 2 parking ban may be declared.

In summary, the Procedure prioritizes non-residential roadways for snow and ice clearing, and - under average snowfall conditions - residential activities would not commence until the completion of all non-residential roadway activities.

The Procedure also includes items related to Severe Snowfall Events (defined as greater than 30 cm in 24 hours), and Snow Emergencies. However, it is silent on the middle ground between the heirarchical approach that applies to "average snowfall" and these severe events / emergency situations.

Future posts will focus on the ability of the Procedure to provide the outcomes outlined in the Policy; on the City's misleading communications regarding the compliance with the Procedure; and on the City's reliance on the Procedure document to justify their inflexibility with regard to residential snow and ice control.

Comments


bottom of page